Off Grid...Chapter 73
6-18
Today it's time for a job that is long overdue. Last year when we put the metal roof on the house we never finished the edges. This has been on Mike's mind for quite some time so we ordered the edging and picked it up from David's last week. Now it's time to get it on the house. Mike thought he would have to buy a tin cutter to do this job but they were kind of expensive for just one small job. That was one of our delays. Just trying to decide what we would use to cut the metal. Next he thought he could use the saws all(reciprocating saw) but that left a sharp and jagged edge on the house. Finally he decided to use his "trusty and favorite" cut off wheel. To do this job Mike has to first cut off the excess metal on the edge around the house and then we can install the new trim pieces. Here is Mike cutting off the excess from our roof on the first side.
The roof trim comes in 10 foot sections. We measure the length and space the edging evenly on the roof. After those are cut to size we put the double sided tape on the roof. Then we stick the roof edging to the tape and then Mike can screw it into the side and top of the house.
Here is Mike screwing in the new trim. We get everything to look good and we work our way down the roof top. The first side of the house is done. After the first side is done we move over to work on the second side. The back trim is different so that will be last to go on. Here is Mike cutting off the excess metal. And cutting off the last piece on that side. After the last piece is cut off we have to clean off the metal debris and filings that are on the roof. I go into the building and bring the blower back for Mike. We like to clean the easy way, lol. He blows off the roof and we measure out where the trim pieces need to go. Next we are ready to tape. Putting the double sided tape down onto the roof. The first pieces of trim are on. Mike is screwing down the trim. Yay the second side is done. Now we just have to do the back piece which is the long one. Here is Mike cutting off the excess on the back of the house. 6-19 We had more rain this morning which messed up our appointment with one of Jimmy's guys. We were hoping to have the house backfilled but it was just too wet to bring any trucks up. We'll have to wait until next week. After the rain stops Mike and I go out to finish the back trim. The back trim doesn't need any tape. This just gets screwed down. Here is Mike screwing on the back trim. And the back trim is done. Well at least the house has a nice finished edge and nothing can get underneath. I would have rather re painted the house before we put the trim on but Mike has a thing about getting material off the floor. Oh well just more cut in work. Little by little we are getting some of the finishing touches done. Our plans for the outside of the house include changing the paint color, adding clover to both sides of the house, planting a garden along the whole back of the house, doing stucco on the front walls, finding plants for the front garden, finding an awning or something for the front doors, and adding a table and chairs. I walked out in front of the house and our front lawn is starting to come in. 6-20 This morning it is very windy and cloudy. It was a rare day because Mike and I both felt relaxed. Woo hoo. We are very rarely chilled with no guilt about it. So for the first time we enjoyed our morning coffee on our new patio. We sat in the plastic chairs that we had from the last 3 years. We plan on buying a round concrete marble topped table and benches for the patio. We decided to go with this because of the maintenance free aspect. It doesn't need to be moved or covered. Once it is in place it will stay forever, lol. We called all different places and no one has one. I found one place that can make one so I asked him to call us when he makes one. I would have thought that at least one would be made for the summer season. I don't think they are big sellers because they are just too hard to move. One table and 3 benched weighs 1200 pounds I have also been on the look out for 2 resin Adirondack chairs with the foot rests. They are so comfortable. We've had 2 different sets over the past 6 years and we love them. Our one chair broke and of course I can't find another tan one. Why do they make outside chairs in blues, reds, yellows, etc.? What does that have to do with outside and natural? So back to our relaxing day. I did some work around the house and Mike went up to work in his building. He installed more ground wires in the electrical box. We also have a ground rod next to the gray building and a ground wire. Next Mike found a piece of wood that he wants to use for an address sign. First he paints it green. After it dries he will add a no trespassing sign and put our address numbers on the sign. Then it will get hung on our front bottom gate. 6-21 First thing this morning as usual I turned on my computer to go on line. My whole computer screen was black. Thinking it was something I did I shut it down and re started it. It seems fine now. That was just another quick update in our life. I hope you all enjoyed the story. Lisa |
Showing posts with label Metal Roofing. Show all posts
Showing posts with label Metal Roofing. Show all posts
Friday, February 22, 2013
Chapter 73...Installing Metal Edging For Metal Roof
Thursday, February 14, 2013
Chapter 5...Getting the Trusses for the House
Hi everyone. Welcome to chapter 5 the week of June 23, 2008.
Now is the time Mike and I enjoy the most. We get to start working without anyone else around. Our goal this week is to get the house enclosed. Monday- Our Roof trusses were delivered. We got 20 trusses, 31 feet long, and they weigh 155 lbs. each. We met the delivery truck on the county road to make sure he could get in. He made it through our right-of-way with no problems. We got them in the gate and past the barn and Mike and I went back up top to the homesite. We could hear the delivery truck driving up and stopping, then backing up and starting all over again. You guessed it. He couldn't make it up our hill. Mike had to go down with the tractor to see if he could help. I stayed up top working on seeding and covering hills with the curlex rolls. Meanwhile Mike is trying everything he can to get the truck up the hill. He even tries to drive it himself but nothing works. The truck just can't make it. After about 30 minutes Mike tells the driver to just unload the trusses on the side of our road. As the driver goes to unload the trusses the strap breaks and the trusses are like matchsticks in the middle of the road. On top of that the trusses are now behind the truck so the driver can't get out. Mike and the driver now have to move each of the trusses by hand onto the side of the road. Now they are right next to our metal roof that also couldn't get up our hill. This is the metal roof with string around it to proptect it from the cows. We are getting quite a collection there. During this whole mess our well man shows up to finish the well. He installed the pump, the bladder tank, a frost free faucet, and the cement cover. At least that went well. So, now instead of working on the house we have to figure out how to get the trusses to the top. Mike and I grab a chain and hop on the tractor. We chain 2 trusses at a time to the middle of the bucket and lift the bucket. Then we slowly drive the tractor to the top. So 10 trips later we finally have the trusses at the top next to the homesite. This took us most of the day. This is Mike coming up the hill
Our lumber delivery also gets there and he makes it up our hill going "backwards". He went backwards because he didn't know if there was enough room at the top to turn around. I give the kid credit, at least he was thinking. He was very suprised to find plenty of room at the top. I wish he delivered the trusses.
Tuesday Ah, finally it's just me and Mike. Yeah! We start working on the front wall of the house. We start out by sliding lumber down the back of the house to the inside.
It's much easier than carrying it down the hill and around the house. We get out the generator, ladder, tape measure, level, saw, pen, t square, screw gun, and screws. Yes, I said screws. We are screwing this entire house together. Mike wants to make it really strong and that it never comes apart.
We only have the front wall to build because both sides and the back are solid concrete. We start out with a 12 foot section in the middle. We build the walls on the floor and then we will stand them up. It's an easy section because there are no windows or doors. We get that done really fast. Next we start to work on one of the walls to the left of the center wall. Oh no, I forgot to bring the measurements for the rough opening of our patio door. Now I have to drive back to the motorhome and get them. Forty minutes later I get back and Mike, always impatient, is trying to put the first truss up by himself. He can be so stubborn but I love him anyway. I get out of the car and help him put the truss up. At least it was an easy one because it sits entirely on the outer wall. Now we get back to working on the other 2 walls. They are identical walls on both sides of the solid center wall. Each one will have a sliding glass door. One in the Kitchen and one in the Living Room. We get the walls laid out on the floor and we stand them up one section at a time and then screw everything together. This is Mike working on the front wall.
This is what we did today
We brace the front walls, put the cow rope back around the house and call it a day. Wednesday- We started out by finishing the front wall. We had some more work to do on the headers(for the patio doors). Mike also had to finish the top plate so we could get the trusses up. Mike then measures and marks the front and back top plate every 2 feet so we know where to put the trusses. This is how we were supposed to get the trusses up: We were both gong to slide 1 truss over the back wall of the house. I was going to hold the back of the truss even with the back of the house and Mike was going to go around front and walk up a ladder while carrying his end of the truss. This would've worked 10 or 20 years ago but not anymore. It was just too much for Mike to do. On to Plan B. Bring the tractor into the house and use the bucket to lift the truss as high as it can go and Mike can lift it the rest of the way. This worked fairly well but it was very stressful and a lot of up and down for Mike. We slid the truss down the wall together, then Mike would go around the hill and into the house, lift the truss onto the bucket, then lift the bucket as I slowly slid the truss foward. When the bucket couldn't go any higher Mike would climb up and lift the truss onto the front wall. Then we would stand the truss up together. At this point I was a nervous wreck because these trusses are very flimsy and I had to hold it steady until Mike could get back up top to screw it in for me. We finally got the system down but we only got 7 trusses up today. This is how our day went. Sliding the truss down the back wall Lifting it up with the bucket Mike lifting the truss the rest of the way This is what we did today Lisa and Mike |
Solar, building
Front Wall,
Metal Roofing,
Roof Trusses,
Tractor